Construction calendar of the World Hearing Center
2003 | Beginning of acquiring own contribution for the future development of the Center |
---|---|
2009 |
May. Submission of the application to receive European Union funds July. Announcement of the competition for design of the new Center September. Winners selection and signature of a contract December. Receipt of a EU funds for the construction in the amount of 2/3 of the total costs, 1/3 was covered by Institute's own means |
2010 |
April. Obtaining a building permission June. Announcement of the competition to build the cold shell of the Center July. The start of construction of the World Hearing Center October. Announcement of the competition to tender for the execution of installation, decoration and outdoor 25 october. The ceremony of laying of the foundation stone for the construction of the Center |
2011 |
March. Putting to use the multi-level garage, complete work on the first stage of construction– cold shell state May. Start of the finishing works |
2012 |
April. Building was put into use 10 may. Grand opening of the World Hearing Center |