Construction calendar of the World Hearing Center

2003 Beginning of acquiring own contribution for the future development of the Center
2009

May. Submission of the application to receive European Union funds

July. Announcement of the competition for design of the new Center

September. Winners selection and signature of a contract

December. Receipt of a EU funds for the construction in the amount of 2/3 of the total costs, 1/3 was covered by Institute's own means

2010

April. Obtaining a building permission

June. Announcement of the competition to build the cold shell of the Center

July. The start of construction of the World Hearing Center

October. Announcement of the competition to tender for the execution of installation, decoration and outdoor

25 october. The ceremony of laying of the foundation stone for the construction of the Center

2011

March. Putting to use the multi-level garage, complete work on the first stage of construction– cold shell state

May. Start of the finishing works

2012

April. Building was put into use

10 may. Grand opening of the World Hearing Center

 